(Completed): IAD01 (Reston) Power Maintenance 10-NOV-11

EVENT START DATE: 11-10-2011
EVENT START TIME: 07:00 EST

EVENT END DATE: 11-10-2011
EVENT END TIME: 17:00 EST

EVENT IMPACT: IAD01 (Reston)

EVENT DETAILS:
CoreSite will be adding additional power to the Reston facility which will require circuit 363 to be shutdown during the maintenance.  Prior to cutting power to circuit 363, the site will be transferred to generator-fed power.  At the completion of the maintenance, and after verification that circuit 363 has been restored, the site will be transferred back to utility power.

Best practice and procedures will be employed throughout this event and we would like to ensure that all relevant IDC tenants are aware of the activity.  If there are any questions regarding this maintenance, please open a support request via the Layered Tech support portal.